    PROJECT DESCRIPTION
    The replacement of 30km’s of 66kV Overhead Feeder from Ulan Mine to the Beryl Substation, in central NSW through to Ulan Mine on an Essential Energy asset. This project involved the replacement of 187 Timber poles with Steel Poles and Conductor upgrade using OPGW and Neon.

    CLIENT
    Essential Energy/Glencore JV

    PROJECT YEAR
    2013