    PROJECT DESCRIPTION
    Caval Ridge Southern Circuit (CRSC) Project – Modifications to existing 11kV overhead lines to feed the new CRSC Overland Conveyor and infrastructure, supply and installation of 7.5km’s of 11kV OHL extension – consisting of the installation of 60 x 21.5m/60kN Concrete poles, Phosphorous conductor  and Double Circuit OPGW Aerial Earth, to reach the new substation (SS-101) located at the South ROM, supply and installation of 11kV power to new substation (SS-112) located at the head end of the overland conveyor, requiring installation of Recloser’s, Capacitor and 800A ABS’s, removal of 11kV O/H line to redundant 10N fill point and modifications and extensions to the existing fibre optic network on the existing overhead lines.

    CLIENT
    BHP Billiton

    PROJECT YEAR
    2017-2018